Greenhouse Project – Timeline, Part 3

2013 Timeline

11/9   http://youtu.be/I5GieLfQ0pM

Members were at the garden this morning to help with trenching the area and assist in whatever help that was needed to square and level in preparation for the footings.  By setting the footings, it properly spaces the framework and allows the area you need to lay your foundation. Ron, Steve & George continued to work till past 5:00. 

Image

11/13 

The insulation was measured and laid against the framework.  Spacers had to placed inside to avoid framework from falling in once dirt  was pushed back against frame.

Image

Image

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s